TOPIC: Integrated change control

Integrated change control 3 years 11 months ago #3298

  • Jimmy Varghese
  • Jimmy Varghese's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Karma: 1
  • Thank you received: 0
Is project plan updates not a part of integrated change control? :dry:

Integrated change control 3 years 11 months ago #3301

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1060
  • Karma: 33
  • Thank you received: 172
It is.

Please see PMBOK Guide 4th Edition, chapter 3.6.2 Perform Integrated Change Control. You will see that it's an output.
The following user(s) said Thank You: Jimmy Varghese
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoRahul KakkarFernando Jr Sinlao LimMary Kathrine PaduaChris PreziottiLazard Toe, ITBMC, MPM, CIPM, PMP, ITILChristian WinterGail FreedmanKevin NasonMichael Sumaquial, PMPSteven Mudrinich, PMPMark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®