Integrated change control 3 years 5 months ago #3298

  • Jimmy Varghese
  • Jimmy Varghese's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 5
  • Karma: 1
Is project plan updates not a part of integrated change control? :dry:

Integrated change control 3 years 5 months ago #3301

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 968
  • Thank you received: 152
  • Karma: 29
It is.

Please see PMBOK Guide 4th Edition, chapter 3.6.2 Perform Integrated Change Control. You will see that it's an output.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Jimmy Varghese
Moderators: Yolanda Mabutas, Ahmed Amin, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Jeremy Raelin, Mary Kathrine Padua, Yasir Mehmood, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP