TOPIC: Integrated change control

Integrated change control 4 years 3 weeks ago #3298

  • Jimmy Varghese
  • Jimmy Varghese's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Karma: 1
  • Thank you received: 0
Is project plan updates not a part of integrated change control? :dry:

Integrated change control 4 years 3 weeks ago #3301

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1085
  • Karma: 34
  • Thank you received: 175
It is.

Please see PMBOK Guide 4th Edition, chapter 3.6.2 Perform Integrated Change Control. You will see that it's an output.
The following user(s) said Thank You: Jimmy Varghese
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
  • Page:
  • 1
Moderators: Yolanda MabutasAhmed AminScott GillardMichael DeCiccoMary Kathrine PaduaERIC BARTLETTGail FreedmanKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPTracy Shagnea, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®