TOPIC: Question Integrated change control

Integrated change control 5 years 1 month ago #3298

  • Jimmy Varghese
  • Jimmy Varghese's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Karma: 1
  • Thank you received: 0
Is project plan updates not a part of integrated change control? :dry:

Integrated change control 5 years 1 month ago #3301

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • PrepCast Instructor
  • Posts: 1207
  • Karma: 38
  • Thank you received: 213
It is.

Please see PMBOK Guide 4th Edition, chapter 3.6.2 Perform Integrated Change Control. You will see that it's an output.
The following user(s) said Thank You: Jimmy Varghese
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
  • Page:
  • 1
Moderators: Yolanda MabutasTimothy EnallsScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonSteven Mudrinich, PMPJohn WolvertonTracy Shagnea, PMPPatrick Floris PhD PMPTy Weston, PMPGenevieve Pluviose, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Six Hours! Join the Live PMP Coaching Class on July 14/15 for just $179. Learn More...