TOPIC: Integrated change control

Integrated change control 8 years 4 months ago #3298

  • Jimmy Varghese
  • Jimmy Varghese's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Karma: 1
  • Thank you received: 0
Is project plan updates not a part of integrated change control? :dry:

Integrated change control 8 years 4 months ago #3301

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1862
  • Karma: 101
  • Thank you received: 461
It is.

Please see PMBOK Guide 4th Edition, chapter 3.6.2 Perform Integrated Change Control. You will see that it's an output.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
The following user(s) said Thank You: Jimmy Varghese
Moderators: Yolanda MabutasMary Kathrine PaduaGabriella Dellino, PMPJoe PangJohn Paul BugarinEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMP, PMI-ACPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudElena MekhanoshinaKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login