fbpx

Reply: Earned Value vs. Actual Costs

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Earned Value vs. Actual Costs

Max. showing the last 6 posts - (Last post first)
9 months 2 weeks ago #29509

Alonso Mena

's Avatar

Could you explain why in MsProject, EV is equal to AC and you can not modify the AC?
3 years 6 days ago #20432

Anonymous

's Avatar

This helped out a lot thank you!
3 years 1 month ago #20067

Chetan

's Avatar

the way you clarified that the EV is the value earned in the project and cost we put to earn it is the actual cost... clarified it all.

thanks
3 years 1 month ago #19796

Anonymous

's Avatar

if earned value is greater than planned value cost so in this case , is there a concern ?
3 years 5 months ago #18828

Crystal

's Avatar

Thank you for this thread! I was struggling with the same thought process and take the exam this afternoon. This really cleared up the confusion!

Crystal
3 years 10 months ago #17462

Anonymous

's Avatar

Khurram, I have an exercise which states: a very small project has total BAC (budget at completion) value of USD100,000 and duration estimate of 5 weeks. After 2nd week of completion in the project, the project is 38% complete. According to the schedule, the project should be 48% completed. Draw the S-Curve and show PV, EV, and AC. I do not have cost incurred to date.
Thanks,
Luis

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login