Welcome, Guest
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Oliver lehman Question

Oliver lehman Question 5 years 1 month ago #2559

  • Sushil More
  • Sushil More's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 9
  • Karma: 0
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?92
o The project was terminated early. At that time, it was over budget and ahead of schedule.
o The project has produced additional deliverables which were originally not required.
o The project has evidently been finished under budget and behind of schedule.
o The project has evidently been finished over budget and ahead of schedule.

Can someone explain, why the correct answer is A and not D? I am not able to understand how do we determine that the project was terminated early.

Sushil.

Re:Oliver lehman Question 5 years 1 month ago #2560

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Sushil,

I went ahead and wrote to Oliver Lehmann himself and asked for his explanation. Here is what he wrote back:
Once the scheduled finish day has passed, a successfully finished project has an SPI of 1.

It was scheduled to be finished by 100% and has achieved 100% completion. 100% divided by 100% is 1.00.

If a finished project has an SPI >1.00, it has either been finished ahead of schedule and the scheduled finish date lies still in the future, or it must have been cancelled.
_________________________________________________

Mit freundlichen Grüßen – Kind Regards
Oliver F. Lehmann, CLI-CP, PMP
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Oliver lehman Question 5 years 1 month ago #2561

  • Sushil More
  • Sushil More's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 9
  • Karma: 0
Thank you Cornelius. This helps.

Sushil
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®