fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Oliver lehman Question

Oliver lehman Question 12 years 6 months ago #2559

  • Sushil More
  • Sushil More's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?92
o The project was terminated early. At that time, it was over budget and ahead of schedule.
o The project has produced additional deliverables which were originally not required.
o The project has evidently been finished under budget and behind of schedule.
o The project has evidently been finished over budget and ahead of schedule.

Can someone explain, why the correct answer is A and not D? I am not able to understand how do we determine that the project was terminated early.

Sushil.

Re:Oliver lehman Question 12 years 6 months ago #2560

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Sushil,

I went ahead and wrote to Oliver Lehmann himself and asked for his explanation. Here is what he wrote back:

Once the scheduled finish day has passed, a successfully finished project has an SPI of 1.

It was scheduled to be finished by 100% and has achieved 100% completion. 100% divided by 100% is 1.00.

If a finished project has an SPI >1.00, it has either been finished ahead of schedule and the scheduled finish date lies still in the future, or it must have been cancelled.
_________________________________________________

Mit freundlichen Grüßen – Kind Regards
Oliver F. Lehmann, CLI-CP, PMP

Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Oliver lehman Question 12 years 6 months ago #2561

  • Sushil More
  • Sushil More's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Thank you Cornelius. This helps.

Sushil
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login