fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: WBS input in all Risk processes?

WBS input in all Risk processes? 12 years 7 months ago #2448

  • Kerri Karel
  • Kerri Karel's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Is the WBS an input into all risk management processes?

Re:WBS input in all Risk processes? 12 years 7 months ago #2451

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Away
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1982
  • Karma: 119
  • Thank you received: 606
Kerri,

The simple answer would be to say "No. The WBS is not listed as an input to all risk processes". But...

Please check your PMBOK Guide on page 274. You'll see that it is not listed in any as an "official" input. When you read through the inputs of the processes you will, however, read that it is sometimes still mentione. (i.e. the Scope Baseline which contains the WBS is an input to Identify Risks.). So the WBS is definitely used in some of the processes.

So it's used in some, but not officially listed for any.
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenAlexander AnikinElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login