management plans in Perform Qual Risk Analysis 14 years 11 months ago #2446

  • Kerri Karel
  • Kerri Karel's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 9
  • Thank you received: 0
Why would you NOT need cost and schedule mgmt plans in the Perform Qual Risk Analysis process. These are inputs in Quantitative! :cheer: