Topic History of : EEF or OPA??

Max. showing the last 6 posts - (Last post first)
12 years 7 months ago #2419

Kerri Karel

Kerri Karel's Avatar

Thanks!
12 years 7 months ago #2410

Adam Leslie

Adam Leslie's Avatar

I agree that this can be confusing. I use Rita's definitions, and it works pretty well:

EEF: existing systems and company culture
OPA: processes, procedures and historical info.

A PMIS is (by definition) a system. Calendars are part of the planning process.

Hope that helps.
12 years 7 months ago #2408

Sagar Mainkar

Sagar Mainkar's Avatar

Hi Kerri,
Even I also wondered why PMIS is a EEF and not OPA.
I think EEF are more to do with regulations(mandatory) than standards(optional).
For eg Certain govt policies and regulations would be already fed into software system of PMIS which makes its use mandatory for PM.
Project Calendar is a guideline and not a regulation.
But this is my logical guess and I leave it to Cornelius for more clarification or correct clarification.
-Sagar
12 years 7 months ago #2395

Kerri Karel

Kerri Karel's Avatar

Why wouldn't a project mgmt information system be an organizational process asset instead of an Environmental Enterprise Factor? Why wouldn't a project calendar be an EEF instead of an OPA? These both seem to be assets instead of culture-related.:ohmy: