fbpx

Reply: Exam-Simulator Question about one choice on a Scop

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Exam-Simulator Question about one choice on a Scop

Max. showing the last 6 posts - (Last post first)
12 years 9 months ago #2109

Cornelius Fichtner

Cornelius Fichtner's Avatar

David,

This question comes straight from the PMBOK Guide. Please check PMBOK Guide version 4 page 122. You will see that "contRact information" is part of the WBS Dictionary.

The real giveaway is this: The WBS and the WBS dictionary are DELIVERABLE oriented and not TASK oriented. Therefore "project tasks" are not part of the WBS / WBS dictionary.
12 years 9 months ago #2106

David Hardin

David Hardin's Avatar

I just took my first 10-question quiz on Scope.

Question 6 was: Information in the WBS does not include?

A - Contract information
B - Quality requirements
C - Responsible organization
D - Project activities

As with most questions I've seen, there is an obvious wrong answer or two, and if one is not obviously the correct answer, then it comes down to choosing your best guess between two.

I chose A, but the right choice was D.

I am wondering if choice A should have been "Contact information" instead of "Contract information."

Obviously Contact information is in the WBS; but (to me) just as obviously, things involving Contracts are not part of the WBS.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®