fbpx
Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: Need a solutions to this question in oliver 175

Need a solutions to this question in oliver 175 12 years 9 months ago #2064

  • Gbolahan Okulaja
  • Gbolahan Okulaja's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 0
46. In a project, a Cost incentive contract has been awarded to a contractor with the following parameters: What is the Point of total assumption (PTA, Breakpoint) of the project?

Target cost:$1,000,000Target contractor fee:$100,000Cost benefit sharing ratio:80%/20%Price ceiling:$1,200,000
Options given as ans:
o $1,000,000
o $1,100,000
o $1,125,000
o $1,200,000

Re:Need a solutions to this question in oliver 175 12 years 9 months ago #2065

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1981
  • Karma: 118
  • Thank you received: 604
Gbolahan,

Since the question is from Oliver Lehmann: Did you ask him directly?
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Need a solutions to this question in oliver 175 12 years 9 months ago #2066

  • Gbolahan Okulaja
  • Gbolahan Okulaja's Avatar Topic Author
  • Offline
  • Junior Boarder
  • Junior Boarder
  • Posts: 20
  • Thank you received: 0
Not yet, you made a point there.
Let me ask him,sometimes you get carried away when you have strong confidence in your teacher.
Gbolahan.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinHarry ElstonJean KwandaDaniel SoerensenElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login