fbpx

Reply: Question on HR Mgmt Knowledge Area..

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Question on HR Mgmt Knowledge Area..

Max. showing the last 6 posts - (Last post first)
13 years 2 months ago #1794

Vijayaraghavan Seshan

Vijayaraghavan Seshan's Avatar

Unfortunately, I do not recollect the source. I have made a list of questions from free sources on the web. My apologies if my original post violates any forum rules.
13 years 2 months ago #1793

Cornelius Fichtner

Cornelius Fichtner's Avatar

Vijay,

Please give appropriate credit and mention where you found this question.

Thanks!
13 years 2 months ago #1792

Vijayaraghavan Seshan

Vijayaraghavan Seshan's Avatar

Hi,
Could someone explain the answer to the following question?

1. Under which process group does the activity of Staffing, Training and Managing a Team fall?
a. Direct & Manage Project Execution
b. Develop Project Team
c. Manage Project Team
d. Acquire Project Team

Answer: a

I was able to guess this. It is also mentioned verbatim in PMBOK (Page 83).

But then this seems to raise a conflict between what is to be achieved via processes mentioned in b,c & d. Can anyone offer a satisfactory explanation?

Thanks
Vijay

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login