Thanks Cornelius for the explanation.
The question from techfaq is as follows:
1)A project manager has created a document and wants to track the changes made in the document. The project manager should create _______.
1.Configuration Management System
2.Project Management Information System
3.Project Management System
4.Control Management System
Correct Answers are : 4
Explanation :
D is the correct answer.
Control Management System tracks the changes.
As per the above the Control Management System would be something that tracks changes. I am confused on this point, as till now I was under the impression that the Configuration management system eg Microsoft VSS, is used for version control,access control and tracking changes.
I would have answered the above question as Configuration management system.
Which is the wrong answer as per them
Is my understanding of the Configuration management system on the right path?
Thanks for your time.
Regards,
Rashmi