Hello,
I'm currently studying Chapter 6 of PMBOK Guide and had a few questions.
1. As mentioned on Pg136, Activity Attributes is one of the outputs of "Define Activities" process. On Pg137, "Activity Attributes" is one of the inputs for "Sequence Activities" and on Pg141, it is mentioned that one of the outputs of "Sequence Activities" is Project Document Updates, which may contain Activities Attributes also.
I'm a bit confused at this because at one place "Activity Attributes" is considered as a "Project Document Update" whereas it's treated somewhat differently in the other process. Is there a link? and how should "Activity Attributes be considered in a general form?
2. On Pg145, it is mentioned that Project Management Software is one of the TT for "Estimate Activity Resources" process. So, what's the difference between PMIS and Project Management Software?
Thank you.
Ashish