TOPIC: Query on Late Start and Early Start

Query on Late Start and Early Start 9 years 9 months ago #169

  • Vasu Ranganathan
  • Vasu Ranganathan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi All,

Thanks in Advance!

I have the following query:

You are creating a your project schedule and notice that for one of your tasks the
Late Start is earlier than Early Start. The task is siad to have:

o Zero Float

o Lag

o Negative Float

o Free Float

Please endeavour to provide the reasoning on the correct answer.

Cheers,
Vasu

Re:Query on Late Start and Early Start 9 years 9 months ago #170

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1373
  • Karma: 42
  • Thank you received: 246
Vasu,

Please ask the person who created this sample question for the correct answer and explanation.

Thank you.

(But without giving it much thought... I'd say "negative float".)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last edit: by Cornelius Fichtner.
Moderators: Yolanda MabutasTimothy EnallsScott GillardMary Kathrine PaduaERIC BARTLETTSteven Mudrinich, PMPCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPTy Weston, PMPGenevieve Pluviose, PMPJoe PangJason YorekLuke HoSimone ChristieAmy MartinezDaniel DewartEmily Rivera

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on Apr 20/21 for just $179. Learn More...