TOPIC: Query on Late Start and Early Start

Query on Late Start and Early Start 7 years 5 months ago #169

  • Vasu Ranganathan
  • Vasu Ranganathan's Avatar
  • Offline
  • Fresh Boarder
  • Posts: 1
  • Karma: 0
Hi All,

Thanks in Advance!

I have the following query:

You are creating a your project schedule and notice that for one of your tasks the
Late Start is earlier than Early Start. The task is siad to have:

o Zero Float

o Lag

o Negative Float

o Free Float

Please endeavour to provide the reasoning on the correct answer.

Cheers,
Vasu

Re:Query on Late Start and Early Start 7 years 5 months ago #170

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Vasu,

Please ask the person who created this sample question for the correct answer and explanation.

Thank you.

(But without giving it much thought... I'd say "negative float".)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last Edit: 7 years 5 months ago by Cornelius Fichtner.
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®