TOPIC: Query on Late Start and Early Start

Query on Late Start and Early Start 10 years 6 months ago #169

  • Vasu Ranganathan
  • Vasu Ranganathan's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 1
  • Thank you received: 0
Hi All,

Thanks in Advance!

I have the following query:

You are creating a your project schedule and notice that for one of your tasks the
Late Start is earlier than Early Start. The task is siad to have:

o Zero Float

o Lag

o Negative Float

o Free Float

Please endeavour to provide the reasoning on the correct answer.

Cheers,
Vasu

Re:Query on Late Start and Early Start 10 years 6 months ago #170

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • Administrator
  • President, OSP International LLC
  • Posts: 1609
  • Karma: 56
  • Thank you received: 296
Vasu,

Please ask the person who created this sample question for the correct answer and explanation.

Thank you.

(But without giving it much thought... I'd say "negative float".)
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC
Last edit: by Cornelius Fichtner.
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPLisa Sweeney PMPHarry ElstonMani Selvan

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Boost Your PMP Exam Prep in Only Eight Hours! Join the Live PMP Coaching Class on January 18/19 for just $179. Click to learn more... OR Click to watch a free session...