TOPIC: Question Procurement questions (Source: Learning Tree)

Procurement questions (Source: Learning Tree) 8 years 1 month ago #1338

  • Azita Dianat
  • Azita Dianat's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 5
  • Thank you received: 0
Can someone please answer and explain the following questions?

Question 1: You have been asked to identify which project needs can be met best by procurement. It is obvious to you that products and services will not be required from outside the performing organization. In this case, the planning procurements and acquisitons would:
A. Be required
B. Sometimes be requiredc
C. Not be required
D. Develop qualified sellers list
Question 2: working in contract closure to determine whether a contractor's deliverables are acceptable, you discover that a contractor is not performing and decide to terminate the contract early. The process used to manage this situation is:
A. Contract closure
B. Administer procurements
C. close project
D. Risk monitoring and control
  • Page:
  • 1
Moderators: Yolanda MabutasTimothy EnallsScott GillardMary Kathrine PaduaERIC BARTLETTKevin NasonSteven Mudrinich, PMPMark Wuenscher, PMPJohn WolvertonTracy Shagnea, PMPJada GarrettMark LacattivaPatrick Floris PhD PMPTy Weston, PMPGenevieve Pluviose, PMP

Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

The PMP Exam is Changing in 2018
Simona and Cornelius
Free Interview - Listen Now

This interview with Simona Fallavollita (LinkedIn Profile) was recorded at the magnificient Project Management Institute (PMI)® Global Conference 2017 in Chicago, Illinois. We discuss the how, what, why and when of the changes that are coming to the PMP exam.

Thank you!
Cornelius Fichtner, PMP, CSM