Do you need customer support or technical assistance? Click here to submit a support ticket...

TOPIC: what to do after project is terminated?

what to do after project is terminated? 3 days 30 minutes ago #22620

  • RITIKA SHARMA
  • RITIKA SHARMA's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Thank you received: 0
Hi everyone,

I am a little confused on what to do next after project is terminated questions. I did read that once the Project Manager gets notified of a project of a phase cancellation or termination , he/she needs to perform the close project or close phase activities. One cant just stop all work.

However, one of the Simulator questions has confused me -

The company has been sold out. Consequently, there is a major shift in direction and strategy. A multiphase project has been cancelled during execution of its final phase and no more budget or work is to be spent on the project. The PMO has assigned the PM to work on another project. Before moving to the other project, what must the PM do?

a. Communicate the status of the project to the team and produce a final report
b. Gain Senior management approval to manage another project
c. Produce the rest of the items on the contract agreement with the supplier
d. Complete the final phase of the project

I selected d . However correct answer is a which i feel is a subset of d.

Can someone please clarify and let me know how to approach these type of questions in the exam?

Thank you
Ritika

what to do after project is terminated? 3 days 13 minutes ago #22621

  • Luke H
  • Luke H's Avatar
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 11
  • Karma: 1
  • Thank you received: 1
Option D: Complete the final phase of the project.

This implies that the project manager should complete the 'project work' in the final phase of the project.

The answer is A, because if the project has been cancelled, the first thing to do is to communicate the news (new status) to the team and all stakeholders and then work on the 'close project or phase' process to archive documents and follow any internal processes for closing the project including the production of the final project report.

I'm not yet a PMP, but this is at least how I understand it.
The following user(s) said Thank You: RITIKA SHARMA
Last edit: by Luke H.

what to do after project is terminated? 2 days 17 hours ago #22634

  • Gabriella Dellino, PMP
  • Gabriella Dellino, PMP's Avatar
  • Offline
  • Moderator
  • Moderator
  • Posts: 97
  • Karma: 2
  • Thank you received: 19
Hi Ritika,

I essentially agree with Luke, in that - if the project has been cancelled during execution of the final phase - you are not supposed to keep working on that phase and get it completed, as option D implies. What you have to do, as Luke points out, is to move to the "Close project or phase" process, which includes what option A describes; i.e., inform the project team about the status of the project and produce a final report.
The project cannot be completed in terms of the activities originally planned; however, the project manager has the responsibility to end it appropriately, by performing all the steps associated to the "Close project/phase" process.

Hope this helps clarify.

Gabriella
Gabriella Dellino, PhD, PMP
PMPrepCast Community Moderator
The following user(s) said Thank You: RITIKA SHARMA

what to do after project is terminated? 2 days 13 hours ago #22641

  • RITIKA SHARMA
  • RITIKA SHARMA's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 8
  • Thank you received: 0
Thank you Luke and Gabriella.

That makes sense! The more I read the questions, the more the answer choice makes sense!
Moderators: Yolanda MabutasMary Kathrine PaduaCynthia Lim Louis, PMPTracy Shagnea, PMPGabriella Dellino, PMPPatrick Floris PhD PMPJoe PangJohn Paul BugarinAmy MartinezEmily Rivera, PMPMohammad Alharbi, PMP, PMI-ACPLisa Sweeney PMPHarry ElstonMani SelvanDenver MartinEric Wanyutu Kahiga, PMPSarah FucciThiago França, PMP®Felix Kamanga, PMPChan RampersaudKyle Kilbride, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
Get PMP Exam Ready in Just Four Weeks! Join the Live PMP Blended Training Course Starting August 10. Click to learn more...