TOPIC: Type of Contract--Procurement Management

Type of Contract--Procurement Management 7 years 5 months ago #100

  • Arslan Hamid
  • Arslan Hamid's Avatar
  • Offline
  • Junior Boarder
  • Posts: 21
  • Karma: 0
which contract has high Risk for buyer
CR
TM
FP

What i know is CR High TM Medium FP low
Please tell me i am right or wrong

Re:Type of Contract--Procurement Management 7 years 5 months ago #104

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Arslan,

We explain this in detail in episode E12.01 Plan Procurements.

Please watch that episode for the explanation. We show a table that explains who (buyer or seller) has more risk for each contract.

Also, here are the official abbreviations for the contracts:
Firm Fixed Price: FFP
Fixed Price Incentive Fee: FPIF
Fixed Price Economic Price Adjust: FP-EPA
Cost Plus Fixed Fee: CPFF
Cost Plus Incentive Fee: CPIF
Cost Plus Award Fee: CPAF
Time and Material: T&M
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Type of Contract--Procurement Management 7 years 5 months ago #109

  • Arslan Hamid
  • Arslan Hamid's Avatar
  • Offline
  • Junior Boarder
  • Posts: 21
  • Karma: 0
I am preparing for PMBOK3 and i have your mp3 format podcast.Can you please explain me which contact got the more risk according to buyer prespective...
What i have learn
CR High
TM Medium
FP Low

Thanks

Re:Type of Contract--Procurement Management 7 years 5 months ago #111

  • Cornelius Fichtner
  • Cornelius Fichtner's Avatar
  • Offline
  • Administrator
  • PrepCast Instructor
  • Posts: 981
  • Thank you received: 157
  • Karma: 30
Arslan,

I apologize! I didn't realize that you had the 3rd edition.

Please also disregard the abbreviations of the contracts that I mentioned earlier. They are from the 4th edition.

So under this light, you are right that FP = low, TM = medium and CR = high from the buyers perspective.

You can also read the following article - they explain each contract type and the risk involved:

zo-d.com/blog/archives/taking-the-pmp-ex...-contract-types.html
Until Next Time,
Cornelius Fichtner, PMP, CSM
President, OSP International LLC

Re:Type of Contract--Procurement Management 7 years 5 months ago #113

  • Arslan Hamid
  • Arslan Hamid's Avatar
  • Offline
  • Junior Boarder
  • Posts: 21
  • Karma: 0
Thanks Please reply me another question regarding contract as well
Moderators: Yolanda Mabutas, Ahmed Amin, Scott Gillard, Michael DeCicco, Rahul Kakkar, Fernando Jr Sinlao Lim, Mary Kathrine Padua, Chris Preziotti, Lazard Toe, ITBMC, MPM, CIPM, PMP, ITIL, Christian Winter, Kevin Nason, Michael Sumaquial, PMP, Mark Wuenscher, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®