fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question

Free PMP® Exam Sample Question 3 years 11 months ago #20790

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


You are managing a renovation project of a vintage house which is to be completed in 12 months at a budget of $100,000. You are 6 months into the project, and you have spent $60,000, but only 40% of the work is completed. How much more will it cost to complete the renovation if the cost performance remains unchanged?

A. $171,940
B. $120,000
C. $149,254
D. $89,254
HINT: Determining how much more it will cost to finish the project is the ETC.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation
The correct answer is D

The total budget or BAC is $100,000. The cost so far or AC is $60,000. You have completed 40% of the work which is the EV or 40% of $100,000 or $40,000. The question is asking for the cost to complete the renovation or the ETC. The remaining calculations are as follows:

ETC = EAC - AC

EAC = BAC / CPI

CPI = EV / AC or 40,000 / 60,000 = 0.67

EAC = 100,000 / 0.67 = 149,254

ETC = 149,254 - 60,000 = 89,254 or the cost required to complete the renovation.


Details for each option:

A. $171,940
Incorrect. The question is looking for the ETC or the cost required to complete the project. This value represents the EAC using the formula EAC = AC +[(BAC - EV) / (CPI x SPI)].

B. $120,000
Incorrect. The question is looking for the ETC or the cost required to complete the project. This value represents the EAC using the formula EAC = AC + BAC - EV.

C. $149,254
Incorrect. The question is looking for the ETC or the cost required to complete the project. This value represents the EAC using the formula EAC = BAC / CPI.

D. $89,254
Correct. The cost required to complete the project is $89,254. The value was derived using ETC = EAC - AC utilizing the formula EAC = BAC / CPI to calculate EAC.

Reference: A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 267
The following user(s) said Thank You: Elena Mekhanoshina
Last edit: by Mary Kathrine Padua.

Free PMP® Exam Sample Question 3 years 11 months ago #20858

  • Mike
  • Mike's Avatar
  • Visitor
  • Visitor
LOL...You said correct option is B and then did all the explanation to say correct answer is D. Seems very focused.

Free PMP® Exam Sample Question 3 years 11 months ago #20865

  • abdu jemal
  • abdu jemal's Avatar
  • Visitor
  • Visitor
please send me your document

Free PMP® Exam Sample Question 3 years 11 months ago #20869

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66
Hello Mike,

Yes, you're right! The answer is D. Thank you for letting me know. I didn't notice that it was B and not D. Keep safe man!

Free PMP® Exam Sample Question 3 years 11 months ago #20881

  • lisa
  • lisa's Avatar
  • Visitor
  • Visitor
so you guys control the replies here to look clean. Scary.....
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login