fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free CAPM® Exam Sample Question

Free CAPM® Exam Sample Question 4 years 1 day ago #20464

  • Arjie Maghanoy
  • Arjie Maghanoy's Avatar Topic Author
  • Offline
  • User is blocked
  • User is blocked
  • Posts: 182
  • Karma: 21
  • Thank you received: 66


All of the following processes fall under the Executing Process Group except:

A. Direct and Manage Project Work
B. Manage Quality
C. Perform Integrated Change Control
D. Manage Team

HINT: Think of what is done in each process, which should help you identify the process that is not part of the Executing Process Group.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C

The Executing Process Group includes processes that are performed to complete the work required to meet the project requirements, while Perform Integrated Change Control process focuses on managing changes to the project, which is performed as a part of the Monitoring and Controlling Process Group.

Details for each option:

A. Direct and Manage Project Work
Incorrect. Direct and Manage Project Work is a process of the Executing Process Group, where the project team performs the work defined in the project plan and carry out approved changes.

B. Manage Quality
Incorrect. Manage Quality, sometimes called quality assurance, is a process of auditing the project to ensure the quality standards are used. This process is under the Executing Process Group.

C. Perform Integrated Change Control
Correct. Perform Integrated Change Control is a process under the Monitoring and Controlling Process Group of reviewing, approving, and managing changes to the project.

D. Manage Team
Incorrect. Manage Team is part of the Executing Process Group, which includes tracking team member performance, manage changes and issues to optimize the project performance.

Reference: Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 25
Last edit: by Mary Kathrine Padua.

Free CAPM® Exam Sample Question 3 years 11 months ago #20557

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
The correct answer is C rather than D as you have explained.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login