You are managing a project to develop a new robot for a mining rescue company. You are currently performing a monitoring and controlling project activity, and you have discovered that some of the project work has not been performed according to the plan. If these issues are not fixed before the next customer inspection, your project might be canceled. You have analyzed the situation, and the corrective action will only require a minor adjustment to a configuration element. What should you do first? A. Implement the corrective actions B. Submit a change request C. Consult the project sponsor D.Delay the scheduled customer inspection HINT: What is the proper change control procedure when an adjustment to a configuration element is required? All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider. Answer and Explanation The correct answer B All of the available answers seem like possible options in this scenario, but the question is specifically asking what you should do 'first'. Although you have already analyzed the situation and you know what corrective actions are required, you must follow the proper change control procedure. A configuration element is a project artifact that has been placed under configuration control. Any change to a configuration element should be formally controlled and will require a change request. Since the question describes a situation requiring a change to a configuration element, the first thing you should do is submit a change request and have it approved before you can implement the changes. Details for each option: A. Implement the corrective actions Incorrect. When a change to a configuration element is required, a change request must first be submitted before the corrective action is taken. B. Submit a change request Correct. A configuration element is a project artifact that has been placed under configuration control. Any change in a configuration element should be formally controlled and will require a change request. Therefore, since the corrective action will require a change to a configuration element, the first thing you should do in this scenario is to submit a change request. C. Consult the project sponsor Incorrect. As the project manager, you have the authority and responsibility to determine how to handle these types of issues that emerge on your project without consulting with the project sponsor. Additionally, a configuration element is a project artifact that requires a change request before any corrective action is performed. Therefore, you should not have to consult your project sponsor. D.Delay the scheduled customer inspection Incorrect. Delaying the customer inspection is an option, but should not be your first choice. Since the corrective action is for a configuration element, a change request is required. Delaying the inspection could be a consequence of submitting the change request, but you need to submit the change request first. Reference: A Guide to the Project Management Body of Knowledge, (PMBOK<sup>®</sup> Guide)</em> – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 112, 115 |
OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®
Company Info
- Home
- PMP®
- PMI-ACP®
- CAPM®
- CIPP/E®
- PDUs
- AI
- Free
- Free PM PrepCast Training
- Free PM PrepCast Exam Simulator
- Free PMP® Practice Exam
- The Free PM PrepCast
- Free PMP® Exam Guides
- Free PMP® Exam Newsletter
- Free PMP® Webinars
- All Free PMP® Exam Resources...
- The Free Agile PrepCast
- Free PMI-ACP® Exam Newsletter
- All Free PMI-ACP® Exam Resources...
- Free CAPM® Exam Newsletter
- All Free PDU Resources...
- Corporate
- Articles
- PMP® Study Guide
- PMP® Certification Cost
- 35 Hours of Project Management Education
- Knowledge Areas & Process Groups
- How to Fill in the PMP Application
- PMP® Certification Exam
- How to get PMP Certification
- PMP® ITTO
- PMP® Exam Questions
- PMP® Certification Bangalore
- PMP® Formulas
- Failed PMP Exam
- PMI-ACP Certification Study Guide
- CAPM Certification Study Guide
- 12 Project Management Principles Explained by Experts
- Project Management Certifications Career Advancement
- PMP vs Certifications
- Project Management Organization Company Benefits
- Project Management Organizations Importance
- Reviews
- Forum