fbpx

Reply: Free PMP® Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP® Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
5 years 2 days ago #16897

Anonymous

's Avatar

Great question! Thanks!
5 years 2 weeks ago #16776

Usman Musa

Usman Musa's Avatar

I got the correct answer right on time and that is great confidence booster for my scheduled test coming on the 16th March. thank you
5 years 3 weeks ago #16699

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project is six months into its nine-month projected duration, and the project manager is reporting that the project is at least three months behind schedule because certain key stakeholders were resistant to any changes that might occur as outcomes of the project. What might have been done differently during project planning to avoid this situation?

A. Better execution of the Manage Stakeholder Engagement process
B. Development of a stakeholder engagement assessment matrix
C. Creation of a comprehensive stakeholder register
D. Establishment of a more robust communications management plan

HINT: Which of the answer choices represent activities that might be performed during the Planning Process Group?

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is B.

The scenario describes a situation where the resistance of certain key stakeholders has caused the project to run behind schedule and is asking what might have been done differently during project planning. Two of the answer choices represent activities which are not associated with the Planning Process Group, and, as a result, those responses can be eliminated. Both of the remaining answer choices represent plausible actions that may have led to better stakeholder engagement. The actual Project Management Professional (PMP)® exam may present questions with more than one correct answer, and the PMP® aspirant must select the 'best' answer among the potentially correct options. In this case, the development of the stakeholder engagement assessment matrix directly addresses the issue described by the question.

The stakeholder engagement assessment matrix is used as a tool during the Plan Stakeholder Engagement process and identifies key stakeholders along with their current and desired engagement level. Classifications for stakeholder engagement may include unaware, resistant, neutral, supportive, and leading. In this scenario, certain key stakeholders were resistant to the project which caused the project to run behind schedule. A stakeholder engagement assessment matrix is the best tool for identifying resistant stakeholders with enough influence to undermine a project. In this case, identifying the current and desired engagement levels of the key stakeholders might have allowed the project manager to take action to address the undesirable engagement levels and prevent the stakeholder's resistance from negatively impact the project's performance. Therefore, of the available options, the development of a stakeholder engagement assessment matrix is the best answer to the question asked.

Details for each option:

A. Better execution of the Manage Stakeholder Engagement process
Incorrect. Better execution of the Manage Stakeholder Engagement process may have addressed the poor engagement levels of the key stakeholders during project execution. However, the question is asking what might have been done differently during project 'planning'. The Manage Stakeholder Engagement process is part of the Executing (not Planning) Process Group.

B. Development of a stakeholder engagement assessment matrix
Correct. A stakeholder engagement assessment matrix is the best tool for identifying resistant stakeholders with enough influence to undermine a project. In this case, identifying the current and desired engagement levels of the key stakeholders might have allowed the project manager to take action to address the undesirable engagement levels and prevent the stakeholder's resistance from negatively impact the project's performance.

C. Creation of a comprehensive stakeholder register
Incorrect. If some stakeholders were not included in the stakeholder register, it might have resulted in these stakeholders being unaware of the project and the project's outcomes. In this case, the key stakeholders were aware of the project and were resistant to the project's outcomes. Additionally, the stakeholder register is created during project initiation rather than project planning.

D. Establishment of a more robust communications management plan
Incorrect. The communications management plan describes how, when, and by whom information about the project will be administered and disseminated. A weak communication plan may or may not have played a role in the poor engagement level of the key stakeholders described by the question. However, another answer choice directly addresses stakeholder engagement levels. Although this answer choice might arguably be correct, of the available options, it is not the 'best' response.

Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 521-522

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login