fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: Free PMP® Exam Sample Question of the Week

Free PMP® Exam Sample Question of the Week 5 years 5 months ago #15509

  • Mary Kathrine Padua
  • Mary Kathrine Padua's Avatar Topic Author
  • Offline
  • Administrator
  • Administrator
  • Posts: 352
  • Karma: 15
  • Thank you received: 122


Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

You are employed by a software development company as a project manager. Your company has a policy that a change control board (CCB) reviews all of the change requests for every project in your organization, and the CCB follows all the recommended activities outlined in A Guide to the Project Management Body of Knowledge (PMBOK® Guide). You and your project team do not serve as members of the CCB. Based on this scenario, which of the following activities might be performed by members of the CCB?

A. Creating a change request
B. Implementing approved change requests
C. Initiating and closing a project
D. Monitoring implementation of approved changes

HINT: Which answer choices are responsibilities of the project manager and the project team?

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is A.

The change control board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting change requests. The CCB can include project stakeholders, and a change may be requested by any stakeholder involved with the project. Therefore, it is possible for a member of the CCB to create and submit a change request.

Details for each option:

A. Creating a change request
Correct. The CCB can include project stakeholders, and a change may be requested by any stakeholder involved with the project. Therefore, it is possible for a member of the CCB to create and submit a change request.

B. Implementing approved change requests
Incorrect. Implementing approved change requests occurs during the Direct and Manage Project Work process, which is the responsibility of the project manager and the project team rather than the CCB.

C. Initiating and closing a project
Incorrect. A project can be initiated by the project sponsor. However, closing the project is typically the responsibility of the project manager. According to the scenario, the project manager is not a member of the CCB. Therefore, even if the project sponsor is a member of the CCB and can initiate the project, this answer choice can be eliminated as at least one of its parts does not hold true.

D. Monitoring implementation of approved changes
Incorrect. Monitoring the implementation of approved change requests is part of the Monitor and Control Project work process. The CCB reviews change requests as part of the Perform Integrated Change Control process rather than the Monitor and Control Project Work process. Therefore, the activities described in this answer choice should be performed by the project manager and the team, not the CCB.

Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 115
Last edit: by Mary Kathrine Padua.
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login