5 years 8 months ago #14903 | |
---|---|
Tonderayi Gowora
|
Thank you so much.
|
5 years 8 months ago #14834 | |
---|---|
Mary Kathrine Padua
|
During execution of your project, a major dispute arises between your company and one of its vendors following your latest review of the vendor's performance reports. Your company's position is that the vendor has failed to meet certain performance obligations under the contract terms. The vendor feels that your company is behind in making payments. What is the best course of action for you to take in this situation? A. Refer this issue to a third party for mediation or arbitration B. File a contract claim and then work directly with the vendor to resolve the issue C. Terminate the contract early, document lessons learned, and find another vendor who can do the work D. Conduct a procurement audit HINT: What is the tool used during Control Procurements to document, process, monitor, and manage disputes between a buyer and seller? All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider. Answer and Explanation: The correct answer is B. When disputes arise on a project, claims administration can be an effective tool to help buyers and sellers reach an agreement and prevent damage caused by litigation and early contract termination. Filing a contract claim and working with the vendor to reach an agreement is a more direct problem-solving approach and therefore the 'best' answer choice. Claims administration also refers to using alternative dispute resolution. However, since mediation and arbitration can be costly, risky, and time-consuming processes, of the choices provided, negotiation is the preferred method of settling disputes and is, therefore, the best course of action for you to take in this situation. A. Refer this issue to a third party for mediation or arbitration Incorrect. Claims administration is used during the Control Procurements process to handle claims, disputes, or appeals between a buyer and a seller. Alternative dispute resolution, which involves mediation and arbitration, can be costly and time-consuming to a project and should only be used if the parties cannot first resolve a claim on their own. B. File a contract claim and then work directly with the vendor to resolve the issue Correct. When disputes arise on a project, the disputing party should first seek to negotiate or work directly with the other party to settle the dispute and document the issue by having one or both parties file a claim. This claim should be processed, monitored, and managed throughout the contract lifecycle. C. Terminate the contract early, document lessons learned, and find another vendor who can do the work Incorrect. Early termination of the contract would be an overreaction at this point since the company has yet to try resolving the dispute using claims administration. Since the early termination of the contract could create delays to the project schedule or added cost, this would not be the 'best' answer choice. D. Conduct a procurement audit Incorrect. From the question, you can determine that the project is in the process of Control Procurements, as your company is still administering the contract and monitoring the vendor's contract performance. Procurement audits, however, are a primary tool of the Close Procurements process and are mainly used to capture lessons learned from the procurement process to help inform future projects. Reference: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 498 |
OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®
Company Info
- Home
- PMP®
- PMI-ACP®
- CAPM®
- CIPP/E®
- PDUs
- AI
- Free
- Free PM PrepCast Training
- Free PM PrepCast Exam Simulator
- Free PMP® Practice Exam
- The Free PM PrepCast
- Free PMP® Exam Guides
- Free PMP® Exam Newsletter
- Free PMP® Webinars
- All Free PMP® Exam Resources...
- The Free Agile PrepCast
- Free PMI-ACP® Exam Newsletter
- All Free PMI-ACP® Exam Resources...
- Free CAPM® Exam Newsletter
- All Free PDU Resources...
- Corporate
- Articles
- PMP® Study Guide
- PMP® Certification Cost
- 35 Hours of Project Management Education
- Knowledge Areas & Process Groups
- How to Fill in the PMP Application
- PMP® Certification Exam
- How to get PMP Certification
- PMP® ITTO
- PMP® Exam Questions
- PMP® Certification Bangalore
- PMP® Formulas
- Failed PMP Exam
- PMI-ACP Certification Study Guide
- CAPM Certification Study Guide
- 12 Project Management Principles Explained by Experts
- Project Management Certifications Career Advancement
- PMP vs Certifications
- Project Management Organization Company Benefits
- Project Management Organizations Importance
- Reviews
- Forum