Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
You are managing a project dealing with a limited amount of resources. Trying to optimize the resources, you have applied a resource management technique which resulted in the critical path of the project schedule to increase. Which resource management technique have you applied?
A. Resource compromising
B. Resource leveling
C. Resource estimating
D. Resource smoothing
HINT: This technique adjusts activity schedules based on the resource constraints.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
Resource leveling is a resource optimization technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over-allocated. Resource leveling can often cause the original critical path to increase.