fbpx

Reply: Free PMP® Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP® Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
6 years 1 week ago #13903

Anonymous

's Avatar

Got it correct!
6 years 2 months ago #13226

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

You are managing a project dealing with a limited amount of resources. Trying to optimize the resources, you have applied a resource management technique which resulted in the critical path of the project schedule to increase. Which resource management technique have you applied?

A. Resource compromising
B. Resource leveling
C. Resource estimating
D. Resource smoothing

HINT: This technique adjusts activity schedules based on the resource constraints.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is B.

Resource leveling is a resource optimization technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply. Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over-allocated. Resource leveling can often cause the original critical path to increase.