fbpx

Reply: Free PMP® Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP® Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
6 years 1 month ago #13144

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project manager is required to anticipate the total final cost for a schedule activity. The past performance shows that the original estimating assumptions are no longer relevant to the present situation. Which of the following approaches should the project manager use to calculate the cost?

A. EAC using new estimate
B. EAC using remaining budget
C. ETC based on new estimate
D. ETC based on typical variances

HINT: EAC is Estimate At Completion; ETC is Estimate To Complete.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is A.

The project manager should determine the EAC with a new estimate. This approach is used only when the original estimating assumptions are no longer relevant in the present scenario.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login