You are the project manager of the CBC project. A new risk has emerged that was not anticipated and was therefore not documented in the risk register. You and your team meet and perform additional risk response planning to control the risk. Which of the following activities have you performed?
A. Risk audit
B. Reserve Analysis
C. Risk Assessment
D. Technical performance measurement
HINT: You are reviewing the project risks.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
Project risks reassessments should be regularly scheduled. The scenario is referring to the Control Risks process that involves risk reassessments.