Which of the following elements of human resource planning would you consider the most important for a project?
A. Risk management activities
B. Quality assurance activities
C. Activity resource requirements
D. Budget control activities
HINT: Consider the inputs to the Plan Human Resource Management process.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 7 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
Activity resource requirements are the primary input to the Plan Human Resource Management process. They are used to determine the human resource needs of a project.