You are the project manager on a construction project. You and your team, along with a subject matter expert, are trying to determine which risks are going to affect the project by going through the project documents in detail. What is this process called?
A. Analyze Risks
B. Identify Risks
C. Plan Risk Responses
D. Control Risks
HINT: You are trying to find project risks.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
Identify risks is the process of determining which risks may affect the project and documenting their characterisitics.