Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
You are the project manager working in a strong matrix organization structure. Which of the following activities do you think is not part of your responsibility?
A. Participate in scope definition
B. Respond to question from Board of directors
C. Lead the weekly team meetings
D. Lead the annual performance review of the team members
HINT: Project team members also report to the functional managers in a strong matrix organization.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is D.
The project manager can provide inputs to the performance process but leading the annual performance review is an activity performed by the functional managers in a strong matrix organization.