Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
You are the project manager on a construction project. In which of the following phases is it not necessary to complete a Phase Review Form?
A. End of Project initiation
B. End of Project planning
C. End of Project closure
D. End of Project execution
HINT: At the end of the project, a project closure document is usually produced.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
It is not necessary to complete a Phase Review Form at the end of the Project Closure phase because approval to close the project is covered within the 'Project Closure' document.