Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

Which of the following tasks should not be performed during project closure?

A. Update lessons learned
B. Secure product acceptance
C. Collect project records
D. Release resources

HINT: Which of theses is a function of Validate Scope process?

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is B.

Securing product acceptance is performed during the Validate Scope process. The rest of the answer choices relate to project closure.