Which type of risk response are you adopting when you build a prototype before the actual product?
A. Risk transfer
B. Risk mitigation
C. Risk avoidance
D. Risk workaround
HINT: You are reducing the probability of the risk.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
Because the probability of the risk is being reduced, this is an example of risk mitigation.