Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
You have recently been appointed as the project manager of a new project. One of the project documents that is part of your company's Organizational Process Assets is one that lists various risk categories in a hierarchical fashion. What is this document called?
A. Risk Register
B. Risk Management Plan
C. Risk Breakdown Structure
D. Influence Diagram
HINT: Think about what type of document displays risk category information in a hierarchical fashion.
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
The Risk Breakdown Structure is a hierarchical representation of risks according to their risk categories. These categories are normally broken down according to project objectives. Remember that any question that contains the word "hierarchy" or "hierarchical" is talking about some type of "breakdown structure" document.