Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

A project manager decides to start the schedule activity only after the predecessor activity finishes. Which type of relationship exists between the activities?

A. Start-to-Finish
B. Finish-to-Finish
C. Finish-to-Start
D. Start-to-Start

HINT: This is the most common type of activity relationship.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a trusted and experienced education provider.

Answer and Explanation:
The correct answer is C.

A finish-to-start relationship means the dependent activity cannot start until the first activity is finished.