A project manager decides to start the schedule activity only after the predecessor activity finishes. Which type of relationship exists between the activities?
A. Start-to-Finish
B. Finish-to-Finish
C. Finish-to-Start
D. Start-to-Start
HINT: This is the most common type of activity relationship.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
A finish-to-start relationship means the dependent activity cannot start until the first activity is finished.