Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
On a project team, members are drawn from various departments. The team members report to Marketing, Finance, and HR Managers, respectively. The project manager has very limited control over them. Which type of organizational hierarchy does this organization follow?
A. Projectized organization
B. Functional organization
C. Strong matrix organization
D. Combination organization
HINT: This is a classical organizational structure.
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
In a functional organization, the team members report to their Functional Managers and the project manager's authority is very limited.