Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
A project manager wants to display and communicate the results of PERT and Critical Path analysis in a simple chart that can be readily understood by those who are not involved in the details of the project. Which of the following charts should he use?
A. Fishbone diagram
B. Flow chart
C. Gantt chart
D. Control chart
HINT: It is a type of a bar chart.
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
A Gantt chart displays the results of PERT and Critical Path analysis in a simple manner using a horizontal bar chart, which can be understood by people who are unaware of the details of the project.