Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
A project manager decides to buy insurance in case of a fire. Which of the following risk response strategies is being used here?
A. Accepting consequences
B. Transfer of risk
C. Removing the risk
D. Reducing the risk
HINT: This risk is being moved to the insurance company.
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
, We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
Insurance is an example of transferring the risk. The risk is not eliminated, it is just passed on to another party, for example, an insurance company.