Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
You are a project manager and you identify that some members of your project team are not able to fulfill their responsibilities. What preventive action will you take?
A. Cross-training & variance analysis
B. Cross-training & additional role clarification
C. Outsourcing work
D. Take disciplinary action
HINT: Preventive actions like these are a result of the Manage Project Team process.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is B.
Additional role clarification and cross-training ensures that all responsibilities are properly fulfilled.