From which of the following elements is the procurement statement of work developed?
A. Project scope statement and OBS
B. WBS and WBS dictionary
C. Project scope statement, WBS and WBS dictionary
D. WBS and OBS
HINT: The procurement statement of work is developed from the project scope baseline.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a trusted and experienced education provider.
Answer and Explanation:
The correct answer is C.
The procurement statement of work is developed from the project scope baseline that includes the scope statement, WBS and the WBS dictionary.