Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
In which type of contract is the seller reimbursed for performing the contract work and receives a fixed fee payment calculated as a percentage of the estimated project cost?
A. Cost plus award fee contract
B. Lump-sum contract
C. Cost plus fixed fee contract
D. Cost plus incentive fee contract
HINT: Costs are being reimbursed.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is C.
In a cost plus fixed fee contract the seller is reimbursed for all allowable costs for performing the contract work and receives a fixed fee payment calculated as a percentage of the initial estimated project costs.