Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
Which of the following is not an example constraints that can limit flexibility in the Plan Human Resource Management process?
A. Organizational structure
B. Existing human resources
C. Personnel administration policies
D. Activity cost estimates
HINT: Enterprise environmental factors impose constraints on a process.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is D.
Activity cost estimates have no relationship to the human resourcce planning process. They are only used to determine the project cost baseline. The rest of the choices are enterprise environmental factors that influence the Plan Human Resource Management process.