Which of the following strategies are suggested to deal with threats or risks that have a negative impact on a project?
A. Avoid, transfer or enhance
B. Exploit, share or enhance
C. Avoid, transfer or mitigate
D. Avoid, exploit or mitigate
HINT: There are four negative risk management strategies.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is C.
Avoid, transfer, mitigate and accept are the four negative risk management strategies.