Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
What does a cost performance index (CPI) of less than 1.0 indicate?
A. Cost overrun of the estimates
B. Cost underrun of the estimates
C. Cost according to the estimates
D. Early progress
HINT: A CPI of less than 1.0 is bad!
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PM Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is A.
A CPI of less than 1.0 indicates a cost overrun.