fbpx
NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: How to proceed in cost reimbursable contract - sample question

How to proceed in cost reimbursable contract - sample question 7 years 1 month ago #9787

  • Joby Samuel
  • Joby Samuel's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Your firm awarded a cost reimbursable contract to a pharmaceutical company for some research related activity. Over time, a large number of changes have taken place on the project and it is difficult to keep track of the status of these change requests. What is the BEST alternative for a Project Manager in this case?

1. Terminate the existing contract and negotiate a new one with the seller
2. Capture all the change requests, along with their current status and follow the contract change control system
3. Terminate the existing contract and sign a similar one based on the same terms and conditions as the earlier one
4. Seek advice from the senior management of your organization

This question was taken simplilearn.com - 200 free questions

How to proceed in cost reimbursable contract - sample question 5 years 9 months ago #14311

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Answer is 2 or B

How to proceed in cost reimbursable contract - sample question 5 years 7 months ago #14916

  • hany azer
  • hany azer's Avatar
  • Visitor
  • Visitor
answer is
(2)
Moderators: Yolanda MabutasMary Kathrine PaduaJohn Paul BugarinJean KwandaElena ZelenevskaiaChristian ElmerChristine Whitney, PMP

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login