NEVER post copyrighted questions. Always state where questions come from. We take copyright violations very serious. Any copyrighted materials will be removed and the posters account will be deactivated.

TOPIC: How to proceed in cost reimbursable contract - sample question

How to proceed in cost reimbursable contract - sample question 2 years 4 months ago #9787

  • Joby Samuel
  • Joby Samuel's Avatar Topic Author
  • Offline
  • Fresh Boarder
  • Fresh Boarder
  • Posts: 3
  • Thank you received: 0
Your firm awarded a cost reimbursable contract to a pharmaceutical company for some research related activity. Over time, a large number of changes have taken place on the project and it is difficult to keep track of the status of these change requests. What is the BEST alternative for a Project Manager in this case?

1. Terminate the existing contract and negotiate a new one with the seller
2. Capture all the change requests, along with their current status and follow the contract change control system
3. Terminate the existing contract and sign a similar one based on the same terms and conditions as the earlier one
4. Seek advice from the senior management of your organization

This question was taken simplilearn.com - 200 free questions

How to proceed in cost reimbursable contract - sample question 1 year 3 weeks ago #14311

  • Anonymous
  • Anonymous's Avatar
  • Visitor
  • Visitor
Answer is 2 or B

How to proceed in cost reimbursable contract - sample question 9 months 4 weeks ago #14916

  • hany azer
  • hany azer's Avatar
  • Visitor
  • Visitor
answer is
(2)
Moderators: Yolanda MabutasScott GillardMary Kathrine PaduaTracy Shagnea, PMPJoe PangLuke HoSimone ChristieAmy Martinez

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login
17-Jul-2019: Free PMP Exam Coaching Webinar with Dan Ryan Register Now...