Which of the following are the most commonly used performance measures for evaluating whether or not work is being accomplished as planned at any given point of time?
A. PV & AC
B. CV & SV
C. SPI, EV & AC
D. AC, EV & PV
HINT: Performance is usually measured in terms of variance from planned values.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is B.
Performance is usually measured in terms of variance from planned values. CV (Cost Variance) and SV (Schedule Variance) are two most commonly used performance indicators.