fbpx

Reply: Free PMP® Exam Sample Question of the Week

Name
E-mail
Your e-mail address will never be displayed on the site.
Subject
Message

Topic History of : Free PMP® Exam Sample Question of the Week

Max. showing the last 6 posts - (Last post first)
7 years 3 months ago #9312

Mary Kathrine Padua

Mary Kathrine Padua's Avatar



Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.

The method of constructing a project schedule network diagram that represents activities as nodes and connects them to show the dependencies is known as:

A. Arrow diagramming method
B. Schedule network templates
C. Precedence diagramming method
D. Activity List

HINT: This is called Activity-on-node (AON) method.

All our questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at www.pm-prepcast.com/freesimulator and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at www.free-pm-exam-questions.com . We are a Project Management Institute (PMI)® Registered Education Provider.

Answer and Explanation:
The correct answer is C.

The precedence diagramming method is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships.

OSP INTERNATIONAL LLC
OSP INTERNATIONAL LLC
Training for Project Management Professional (PMP)®, PMI Agile Certified Practitioner (PMI-ACP)®, and Certified Associate in Project Management (CAPM)®

Login