The method of constructing a project schedule network diagram that represents activities as nodes and connects them to show the dependencies is known as:
A. Arrow diagramming method
B. Schedule network templates
C. Precedence diagramming method
D. Activity List
HINT: This is called Activity-on-node (AON) method.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is C.
The precedence diagramming method is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships.