Which of the following is not a planning component of the Define Activities process?
A. Control account
B. Milestone list
C. Rolling wave planning
D. Decomposition
HINT: Two of the choices are tools and techniques of the Define Activities process while one of the choices is an output of the Define Activites process.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is A.
Rolling wave planning and decomposition are the tools and techniques of the Define Activities and the milestone list is an output of the Define Activities process. Control accounts are a planning component of the Create WBS process.