Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
Which of the following activities is not concerned with developing the project charter?
A. Documenting the business needs
B. Project justification
C. Collecting output of the planning processes
D. Current understanding of the customers' needs
HINT: The project charter is a high level document that authorizes a project.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is C.
The output of the planning processes is collected to develop the Project Management Plan and not the project charter.