Hello everyone! Here is this week's free PMP® exam sample question from the PM Exam Simulator.
Which of the following project management processes is not included in the Monitoring & Controlling process group?
A. Control Scope
B. Perform Integrated Change Control
C. Control Quality
D. Perform Quality Assurance
HINT: Perform Quality Assurance is a process of quality auditing.
All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at
www.pm-prepcast.com/freesimulator
and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at
www.free-pm-exam-questions.com
. We are a Project Management Institute (PMI)® Registered Education Provider.
Answer and Explanation:
The correct answer is D.
The Perform Quality Assurance process belongs to the Executing process group.